Access

Clear access

Scaffolding

Trenches

Space to put boards

Housekeeping

All materials removed

Floors swept

Cleanliness

Building Watertight

Roof

Doors

Windows

Porch/Bay window

Carpentry

Stairs fitted

Nogged to underside of stairs

Ceilings nogged

Loft hatch nogged

Bulkhead built

Door linings

Window boards

Studwork

Ply

SVP boxings

Plumbing

All plumbing complete

All pipework fixed in position

Electrics

Complete

Cables fixed and marked for position and height

Insulation

All insulation installed

Cavity wall insulation

Quality Checklist

All board work complete & fixed correctly

All insulation and fixings installed

Correct boards used

Wall, reveals and pipecases square and level

Plaster or jointing finished to a satisfactory standard

All materials removed from the plot

Floors swept and scraped

All materials tidied outside of plot and covered correctly


General Comments & Instructions

File Upload - PDF or JPG accepted